| Sometime
on Friday, apparently after the markets closed, the Connecticut Department
of Public Utility Control ("DPUC")
issued its long awaited "Draft
Decision" on proposals for "Project 100", including
the FuelCell Energy based proposals under that program that were previously
recommended by the Connecticut Clean Energy Fund and which FCEL
has been saying will result in 68 MW ($200M) worth of orders for the
company.
This Draft Decision
is a big lump of coal for FCEL this holiday season. Of the proposed
projects involving FCEL, only 16.2 MW worth are recommended in the Draft
Decision published on Friday. This means that if the "Final Decision"
(currently expected on January 9) ends up being the same as the "Draft
Decision", the $200M worth of orders that FCEL has been saying
it expects will, presumably (on a straight proportional basis), end
up being more like $47.6M. (Actually somewhat less, because some of
the 16.2 MW in the approved projects' total rated generation capacity
will come from a "turbo expander energy recovery generator"
involved in one of the projects rather than from FCEL fuel cells. See
discussion below.)
Excerpts from the
DPUC Draft Decision:
- "The OCC
[Office of Consumer Counsel, "the State of Connecticut’s
advocate for all utility ratepayers. OCC seeks to ensure just and
reasonable rates and reliable utility service for customers of Connecticut’s
electric, gas, telephone, and water utilities . . ."] recommends
that the Department accept only those projects which create a limited
cost impact to ratepayers and which provide co benefits to the generation
of Class I renewable power. In addition, OCC suggests that
the Department limit the risk associated with the rapid deployment
of a fuel cell (FuelCell Energy DFC3000)
technology that in the proposed project size has not been proven in
a commercial setting over a sufficient time period."
[The basic technology in the DFC3000 is the same
as in any other FCEL product configuration. Why is a ratepayer advocacy
agency like the OCC making technology risk assessments? What expertise
does the OCC have in this regard? Why would a "suggestion"
from OCC involving risk assessment be given any weight?]
- "OCC’s
testimony noted that only two biomass and one landfill gas projects
provide financial benefits to ratepayers, totaling over $70 million.
The remaining eight projects, all, will increase costs to ratepayers.
Of those eight, three projects, totaling 56.4 MW –
the Brassworks Fuel Cell, Triangle Fuel Cell and Bridgeport Fuel Cell
[all FCEL based proposals],
stand out as being by far the most expensive and least justifiable
under a “financial benefit to ratepayers” statutory standard.
These three projects produce total cumulative costs to ratepayers
of $651 million, with project costs to ratepayers between $190 million
and $256 million a piece. OCC did not recommend acceptance of the
proposal for a contract from any of these three projects. If these
three projects were not approved by the DPUC, the total impact on
ratepayers from the portfolio would drop from $651 million to approximately
$113 million. On an annual basis, the cost would drop from approximately
$35 $45 million to $2.5 $9.5 million if the three projects were rejected."
- "There is
a significant difference between the proposed contract prices of the
biomass projects and landfill methane gas and those of the fuel cell
projects. In 2009, the price for the three biomass projects is between
12.3¢/kw and 12.9¢/kw. South Norwalk is a bit higher at
14.4¢/kw. On the other hand, the lowest cost fuel cell
is 17.4¢/kw and the rest are between 18.5¢/kw and 20.3¢/kw.
This compares to an avoided cost of approximately 12.5¢/kw."
- "According
to the analysis by the EDCs [?], the overall
impact would be an increase of $787.6 million if all eleven projects
are approved. This is extremely expensive compared to other generation
sources. The Department, therefore, will not approve all of
the projects as CCEF has recommended. Instead, the Department will
attempt to minimize the cost to ratepayers, while meeting the legislative
intent to contract for 125 MW of renewable resources at this time."
- "The
Department believes OCC’s objective to minimize the costs to
ratepayers is appropriate and therefore we generally agree with their
recommendations."
- "The
fuel cell projects may never provide economic benefits to ratepayers.
All of the fuel cell projects selected a pricing option that
links their contract rates to natural gas prices. Their prices will
decline if gas prices decline but they will increase if natural gas
prices increase. This does not provide the hedge one would usually
associate with the renewable resources." [H2FC's
view: This has been abundantly clear from the outset: calling
natural gas fueled generation capacity "renewable" has always
been a politically convenient fiction. Everyone involved in the Project
100 process with even a basic understanding of the issues involved
has known this all along. What caused this sudden revelation at DPUC?
Did the commissioners, who are politicians, get cold feet in light
of the OCCs cost analysis? Are the commissioners, afraid of the political
heat that could result from the impact on ratepayers, now looking
for a way out and therefore suddenly "realizing" that natural
gas fueled fuel cells aren't really renewable?]
- "It
is very clear from the analysis that the biomass and landfill gas
projects are significantly less expensive than the fuel cell projects
on all relevant measures. Three of the projects, both Clearview
projects and SNEW Bio Fuel, are expected to provide economic benefits
to ratepayers over their contract lives totaling approximately $72
million. The other biomass project, PRE, is estimated to be over market
by approximately $17.5 million. Plainfield is a larger project at
30MW. In that context its overall impact is minor compared to the
alternatives offered by the fuel cell projects. Plainfield is significantly
lower cost than any fuel cell project on a cents/kwh or $/kw basis.
The Department will therefore accept each of these projects, for a
total of approximately 93 MW."
- "On
the other end, Brassworks [FCEL],
Bridgeport [FCEL] and PureCell
[UTC] must be rejected.
These are the most expensive projects on a ¢/kw and
$/kw basis. Brassworks (21 MW) and Bridgeport (14.4MW) have a huge
negative total impact on ratepayers of $255.6 million and $190.9 million.
The 1MW PureCell project is the smallest project proposed. Due to
its small size, its overall impact is only $6.6 million but it would
not be appropriate to approve such an expensive project simply because
it is so small. This project ranks 10th on the list on cost ¢/kwh
and $/kw basis."
- "To summarize,
the Department will approve seven projects, totaling approximately
109.2 MW. These projects are:
- Clearview
Renewable Energy, LLC biomass 30.0MW
- South Norwalk
Electric Works landfill gas 30.0
- Clearview
East Canaan, LLC biomass 3.0
- Plainfield
Renewable Energy biomass 30.0
- Waterbury
Hospital Fuel Cell 2.4 [FCEL - pure
fuel cell]
-
Stamford Hospital Fuel Cell 4.8 [FCEL
- pure fuel cell]
-
DFG-ERG Milford, LLC Fuel Cell 9.0" [This
is the FCEL based proposal involving Enbridge that includes a
gas
expansion turbine. Notice that the three FCEL based projects
that DPUC says it will approve (16.2 MW) plus the three that DPUC
says it will reject ("56.4 MW") total 72 MW, 4 MW more
than the 68 MW that FCEL has been talking about. The discrepancy
is presumably due to the fact that the total rated capacities
of the big FCEL based projects don't all come directly from the
fuel cells. For example, the 9 MW total capacity of the "DFG-ERG
Milford" project is partially from the fuel cells and partially
from the gas expansion turbine. This also means that the 16.2
MW worth of FCEL based projects that DPUC says it will approve
will lead to less than 16.2 MW worth of orders for FCEL. Probably
more like a total of 12.2 MW (~$35.9M), since the the basic 2.2
MW "DFG-ERG" uses 1.2 MW worth of fuel cells and 1 MW
worth of gas expansion turbine.]
Obviously an extremely
negative Draft Decision for FCEL that, if it becomes final, will throw
a major monkey wrench in FCEL's plans for ramping up its production
capacity and its schedule for realizing economies of scale.
The Draft Decision
does contain the following right at the top:
"This draft Decision is being distributed
to the parties in this proceeding for comment. The proposed Decision
is not a final Decision of the Department. The Department will consider
the parties’ arguments and exceptions before reaching a final
Decision. The final Decision may differ from the proposed Decision.
Therefore, this draft Decision does not establish any precedent and
does not necessarily represent the Department’s final conclusion."
So things could change for the
better by the time of the DPUC's "Final Decision" on January
9. But it seems to H2FC that for any or all of the projects rejected
in the Draft to be brought back to life in the Final Decision, a lot
of political pressure will have to be exerted on the DPUC commissioners
by the better known CT politicians who have made a lot of noise over
the years about their support for the development of a major fuel cell
industry in CT. In other words, CT's Congressional delegation, state
legislators and Governor will have to to step up and be prepared to
take the heat for the utility rate increases that the projects involved
will entail.
It could
happen. But H2FC is not holding its breath. Politicians hate nothing
more than putting themselves in a position where they can be blamed
for costing voters money: they hate this even more than they love talking
about creating new industries and new jobs. So to H2FC, the prospects
for revival of the projects that were rejected in the Draft Decision
seem pretty slim.
The effect of the
Draft Decision on FCEL's share price over the coming days is difficult
to predict with any confidence. How many FCEL investors will be paying
enough attention during the next two holiday weeks to even notice the
publication of Draft Decision, especially if no one issues a press release
about it? (Note that the short
sellers, who tend to be market professionals, are probably more
likely than retail longs to be keeping track of the dates and to be
seeking out the information for themselves.) H2FC doesn't expect a press
release from the DPUC or CCEF about the Draft Decision since they didn't
issue one on Friday when the Draft was published. Will FCEL say something?
It sure seems like the company has to: the Draft Decision, even if only
a "draft", is still very highly material for the near term
prospects of FCEL, and if the company remains silent it exposes itself
to charges of withholding critical information from its shareholders.
Will the company issue a release in which management provides more happy
talk about how it expects the Final Decision to be much more favorable?
Who knows. On general principal though, H2FC expects the stock to take
a good sized hit over the next couple of trading days.
Another problem for
FCEL: under threat of a veto by President Bush, the federal energy bill
signed
into law on December 19 was stripped of extensions of investment
tax credits ("ITCs") for capital expenditures on renewable
energy projects that are currently set to expire at the end of 2008.
(H2FC can't find a single news report that explicitly talks about the
$1,000/kw
ITC for fuel cells, put presumes that it was left out of the
energy bill along with the ITCs for wind and solar.) Nothing under Project
100 will be operational by the end of 2008, so without an extension
of the federal ITC, nothing under Project 100 will qualify for a federal
ITC. This will leave a very big hole in the required project financing
- $1M for every megawatt - making it seem likely that none
of the financing deals that FCEL is depending on for Project 100 will
close unless and until a veto-proof extension of the fuel cell ITC is
passed by Congress. (This is the risk a company runs when it bases its
entire business plan on government subsidies. H2FC has been warning
about this for years with respect to FCEL.)
Previous H2FC discussion of "Project
100":
12/17/07 Additional
steps required subsequent to final DPUC approval
9/2/07 Discussion
in notes from Q3 conference call
8/22/07 Two
Connecticut Utilities Submit 68 Megawatts of FuelCell Energy Power Plant
Projects to Connecticut Department of Utility Control
6/10/07 FCEL
management says it expects final CT project approvals of all 68 MW in
mid to late August
3/26/07 H2FC Update: Connecticut
Clean Energy Fund, Under Round 2 of Project 100, Selects 11 Renewable
Energy Projects 68 MW worth of FCEL based projects
12/27/06 FuelCell
Energy Submits 98.6 MW of Bids for Ultra-Clean, Multi-Megawatt Power
Plant Projects in Connecticut Proposals Range in Size from
2.4 MW to 28 MW
News subsequent to this Update:
12/25/07 DPUC
Chooses Energy Projects Hartford Courant
12/24/07 Connecticut
Slights FuelCell Energy Forbes
12/24/07 FuelCell
Receives Preliminary OK From CT Utility for Order, but Stock Falls
AP
12/24/07 FuelCell
shares fall after size of DPUC projects disappoints Reuters
12/24/07 1:00 PM ET FCEL
closes at 10.06, down 2.82 (21.9%) from Friday's close, volume 6.54M
(3m avg. vol. 1.237M) | 4th
biggest NASDAQ decliner on Monday
12/24/07 FuelCell
Receives Preliminary OK From Connecticut Utility for Order, but Stock
Falls "The decision disappointed some investors who
hoped for a bigger part of the state's efforts to reduce energy consumption."
AP [Just maybe because FCEL management has
been saying for months that it fully expected to get the entire 68 MW.]
12/24/07 Premarket
Movers: FCEL "On the losing side in the early session
were shares of FuelCell Energy Inc., after Connecticut's state utility
commission reportedly decided to grant a smaller contract to the Danbury-based
alternative energy company, disappointing investors who hoped for a
bigger slice of the state's efforts to reduce energy consumption. The
final decision has not yet been released. The stock had rallied in recent
weeks, as investors anticipated a larger award. "We believe the
stock will be under meaningful pressure given this outcome which will
slow FCEL's potential cost reduction plans given lower than potential
production levels," said JPMorgan Securities analyst Brannon Cook
in a note to clients . . ." AP
12/24/07 Connecticut
Department of Public Utility Control Issues Draft Decision Approving
16.2 Megawatts of Projects Using FuelCell Energy Power Plants
DPUC's Decision Fosters Clean Energy Projects FuelCell Energy, Inc.
"These selections firmly establish fuel cells' role in deploying
ultra-clean energy capacity. With their 24/7 reliability, fuel cells
can solve electric grid congestion while reducing the need for new generation,
transmission and distribution investment. Our fuel cells provide this
power with virtually no emissions.'' For FuelCell Energy, these project
approvals represent an important achievement that represents an estimated
$43 million in potential product sales" FCEL Press Release
[So the strategy at FCEL is to simply pretend that
this is not a huge disappointment. Meanwhile, FCEL opened down more
than $2 this morning.]
market close at 1:00 PM ET on 12/24/07
 |